Community Hub Project
@ 2008 Leger Road
Our Journey...
Oak Hills is working through a 5 year planning process to give guidance to our programming, events and a new building, the "Community Hub" @ 2008 Leger Road. This project is in partnership with Terwillegar Riverbend Soccer Association (TRSA), the City of Edmonton (COE), the Government of Alberta (GOA), and the Edmonton Federation of Community Leagues (EFCL).
Check out the latest updates below to follow the timeline of the project from initial engagement to our current phase.
2024 - Phase 1 Construction
The Hub project needs you! Can you help in at least 1 of 3 ways:
As little as $5/month
A lot less than Netflix!
Until Sep 12th 2024
Get a 50/50 Ticket
Sign Up for Updates
Progress, rental & more
September 2024 - Parking Lot, Utilities & Floor Slab
Work continues to move along on schedule, if you look closely there are a lot of changes each day though it is easy to pass by and just see a lot of dirt and mud still! We have storm drains installed under the parking lot and connection to building, as well as all the under-building services are installed and ready for connection when we get to that stage. The parking lot will be done as soon as possible through September with a lot of site work already done as of early Sep. We also need to get the floor slab poured and cured before freeze up to avoid further heating costs associated with concrete work in the colder months.
Transit/Sidewalk Closure Sep 16 - 20th
Monday Sept. 16th until Friday Sep 20th the ETS stop south of our site will be closed while sidewalk work is being done. See the small red hashed section on the image above. ETS has provided alternate stop service as listed to the right.
Take a StoryWalk by our site with Astronaut, Chris Hadfield
Come by the north side of our project site (near the playground) to go on a StoryWalk with Chris Hadfield brought to you by Edmonton Public Library. While you’re there have a look at our progress!
August 2024 - Piling & Foundation Work
Over the late days of July and early weeks of August our site will see auger piles being drilled and poured for the foundation. This will be followed with grade beams and underground work for the building services. Once all underground work is completed we should start to see a proper flooring slab poured which will be the footprint of our new building. A lot of this work will be completed through late summer, and will function alongside other service installation of items such as power, water, sewer etc. We expect to have walls up, roof on and building enclosed by snowfall. Late August and early September we should start to see parking surface installed. The project committee will soon be meeting to start planning interior color choices and finishing.
A few things to note for our community members. Construction times are M-F between 7am and 9pm. There will be times where there are obstructions on roadside near the site. We were made aware that the bus stop (pictured below), adjacent to the south aspect of our site, will have several days of disruption while the foundation items are being poured to allow for staging of equipment there and access to the site border. This will be managed by ETS and signage/communication will precede this a few days prior on at the stop affected.
Early August - Soil starting to be moved and excavated
Late August - Forms, underground services and pre-slab work being done
Mid August - Pilings being drilled and poured
July 2024 - Site Work
Trees have been relocated around the site that would otherwise have needed removal due to building construction. Site survey markers are up for the general layout, and fencing for construction and tree-protection are up. The entire area is fenced off for safety, the construction area will only be a small area of the field. We plan to keep as much field, hill and trees intact for community outdoor activity use (and hopefully a future skating area!)
June 2024 Construction Begins
Here's what's expected to be happening on site in the next 30 days as construction begins:
Tree relocations
ATCO gas line installed
EPCOR site services installed
Fencing setup & sitework begins
Molok waste bins on site
Check out a 3D rendering fly-through of our future home!
June 2024 Groundbreaking
Oak Hills Community Hub construction officially kicked off on June 1st. Oak Hills CL and Terwillegar Riverbend Soccer Association celebrated together and were joined by many important volunteers, board members, supporters, funders and community engagers. This event was a small celebration for those along for the ride so far. We were honored to share the celebration with Rhaki Pancholi (MLA Edmonton-Whitemud), Tim Cartmell (City Councillor Ward pihêsiwin), Shannon Fitzsimmons (Director Facility Planning and Design COE), and Jenn Parsonage (President EFCL) among many other key supporters and volunteers.
As our project progresses, our group size gets bigger every photo! The excitement is building. Get involved!
Sign Up Here - be first to know about opportunities to get involved, and learn about how to rent or access the facility when the time comes!
March 2024
We have spent the first weeks of the new year preparing for the construction tendering process. This included updating the floor plans and drawings for a new Phase 1, which is a slightly reduce footprint. Following this, the Invitation for Tender (IFT) was initiated early March and has now closed as of March 26th. Construction / trade bid reviews are ongoing which will quickly roll into a building permit and spring construction phase.
How about the building and layout? Well, as was shared earlier, the old Phase 1 (from 2023) will now be split into two phases to help balance costs and functionality. We are thrilled to have found a path forward. Read on for the latest...
Phase 1 (2024) - Community Hub
Clubhouse (~550 sf): Community events & programming area, social gatherings, courses, meetings, eSports, sports/moving nights, etc.
Community Lobby (~400 sf): Casual social gathering, washrooms, warming area, extension of clubhouse space, food & drink serving
Soccer & Community Storage (~1000 sf): Community sports, facilities storage
Office/Admin (~100 sf): TRSA/OHCL operations, facility management
Clubhouse Features
Gatherings of up to 90 people
Patio area (shared external AV)
Hybrid events/gatherings
Presenter/Room cams
Laser projector
Surround audio
Room-wide microphone
Share video/audio to lobby
Clubhouse Usage & Functionality
Seated events (20-40 people)
Speaker/panel series
Workshops/seminars
Small group dining/tasting
Clubs & hobby groups
Film screenings/movies
Meetings
Non-seated events (40-60)
Social / sports night
Reception / Gala
Fundraisers
Birthday parties
Fairs / Markets
Gallery/art events
Fitness / Wellness Activities
Community Lobby & Multiuse Area
Features:
Casual gathering space, waiting area pre/post events
Ability to join the Clubhouse audio / video feeds to allow for expansion into this space for larger gatherings
Break-out space for events/meetings
Food service / reception area includes counter, fridge , sink/wash up area
Washrooms
Signage / Facility Schedule
Exterior & Grounds
Priorities for the building exterior:
Clean, modern look
Low maintenance, high quality exterior finishing
Awareness of other buildings, community age and spirit
Accessibility & Parking to reduce impact on neighbours
Traffic impact considerations in terms of building placement, access/egress and existing traffic issues on Leger Way/Road
Site Plans & Landscaping Priorities:
Improvements to sledding hill nearby
Open parks events area maintained for events/casual use
Future skate-eight/loop
Future community gardens
Native trees, shrubs, grasses augmented throughout
Lighting and safety considerations to reduce vandalism/crime
Safety & Security
Monitored security / alarm
HD video recording & monitoring
Parking lot lighting and video monitoring
Door access control
Fire, water, glass break/motion
Phase 2 & Phase 3
To keep this project on track, we have made the full project a 3-phase plan.
Phase 1 is explained in detail above and is being constructed 2024 with this current round.
Phase 2 is an anticipated expansion to add functional space to the Community Hub as it grows into its operations, based on further needs & funding. Phase 2 is drafted to include: outdoor/indoor kitchen space, completed patio area, further storage and an additional seniors event/program area.
Phase 3 would be the full build-out of our vision, and would include a banquet space (The Great Hall), indoor winter-sport/skate change area, ice maintenance/garage area, commercial kitchen and larger event lobby space with separate access/egress.
2023 - Finalizing Design & Initiating Build Phase
Nov 2023 - Engagement is in! We have been given direction by our boards to find a path forward to get a community hub built, while maintaining the original budget. The team will be adjusting the project scope to accommodate the budget shortfalls created by inflationary pressures. The basics of this means we will be reducing the building footprint, and going back to the key deliverable items that our communities have identified as priority items. We have also reflected on how this scope adjustment could impact our business case & operational feasability. We have been working the past 4 weeks on these items and feel we have found a path forward that will keep the required scope and on budget. The construction team has been given these inputs and are preparing the adjusted building floorplan for final comment later this month. Next steps will be to submit an amendment to our development permit so there are no surprises down the road in that department.
We are now aligning for a spring 2024 build initiation which would wrap up in late 2024.
Oct 2023 - We've gone to construction tender for the project, which resulted in some shocking findings - construction, materials and labor costs have inflated significantly since our initial budget was prepared during the planning phase back in 2022. Although we were anticipating some increased costs due to market changes, no one on the project was prepared at the scale of the change reported back. It was immediately clear that Phase 1, in its current form, is not in the margins of possibility for a 2023/24 build without some significant scope or funding adjustments. The project team had to take a pause while we delivered this info to our respective boards for further direction, feedback and comment. The team spent this down-time preparing multiple options, given various directional outcomes. We are currently awaiting stakeholder feedback over the next 4 weeks, after which time the team is reconvening to deliver the direction to our construction team.
July 2023 - We're thrilled to share the latest update on our community project. An important milestone has been achieved: the Development Permit for our new community hub is now approved! We're enthusiastically advancing to the next stage—the building permit process—and finalizing the smaller, yet essential, finishing details. We have also received the official address of our new hub: 2008 Leger Road. Thanks to your continuous support and the relentless commitment of our volunteers, we're making significant strides towards realizing our shared vision.
Summer has arrived and it brings exciting opportunities to learn more about our community hub. You're invited to join us at the Southwest Edmonton Farmer's Market. Save the dates, we will be there next on August 2nd and 23rd. Drop by to see the floor plans, inquire about programming and events, and explore ways to get involved. We can't wait to meet you at our tent, conveniently located next to the information tent!
We're proud that our community hub will also be a home for the Terwillegar Riverbend Soccer Association (TRSA). This exciting partnership means that our hub will not only serve as a community space but also as a vibrant base for local soccer activities. TRSA will have a dedicated soccer storage area, an office, and shared access to the hub to host soccer gatherings, programs, and events locally. We're thrilled that this project will be a central location for community initiatives.
Our community hub is being designed to be more than just a building—it aims to be a dynamic, high-tech gathering place for our community, featuring three unique indoor spaces. The first is the Clubhouse, our hybrid-ready space equipped with top-notch video & audio streaming capabilities. Here, you might see yoga classes, language learning sessions, art workshops, birthday parties, or other celebrations allowing you to join either in person or virtually. The second space is the Fireside Lounge, designed to be a cozy area for smaller social gatherings. Imagine relaxing by a warm fire, engaging in friendly card games, or simply enjoying good company. The third space is our large Community Lobby, designed with the purpose of fostering spontaneous connections and new relationships.
And for those beautiful summer months, we hope to provide a stunning setting to make the most of Edmonton's fine weather. We hope to one day include indoor-outdoor components of the building, including a heated patio, outdoor firepit, and an outdoor kitchen complete with a pizza oven. Come winter time, imagine an improved toboggan hill, ice-skate path, and cross-country skiing around the Bryan Anderson Athletic Grounds, ending your adventure at an outdoor firepit and warming area to socialize with others braving the winter cold.
Our goal continues to be to create a hub that embodies YOUR vision, and we're thrilled to announce that we're turning that vision into reality. We're breaking ground later this year and are anticipating opening the doors to our new hub in early 2024!
We're on an exciting journey and we want you to be a part of it. Sign up for hub updates, share your ideas, tell your neighbours, and get involved. Together, we're making our community hub a reality!
Looking forward to seeing you at the market!
Some of the team at SWEFM - Come Visit
Jun 21, Jul 12, Aug 2, Aug 23, and Sep 27th to meet us in person
May 2023 - The Community Hub Committee made strides by submitting our Development Permit, despite a slight delay due to the comprehensive evaluation of building sustainability, cost-effectiveness, environmental initiatives, and functionality to serve our community. The plans, reflecting community engagement, balance functionality for all seasons, the potential for expansion, and the need for both walkability and parking space. We've also focused on reducing operational costs by evaluating geothermal systems, maximizing site placement, planning for heat recovery systems, and future solar power installations. The Hub's floor plan embodies adaptability, multifunctionality, inclusivity, and safety, facilitating simultaneous programs for all generations. Our dedicated team of volunteers, consultants, and contractors continue to work diligently to create a sustainable, welcoming Hub within our financial means.
Get engaged! May through September 2023 we will be attending 6 Farmer's Market days as a means to engage with you, and hear how you envision using the space!
Come visit us on one of the following: May 17th, June 21st, July 12th, August 2nd, August 23rd, September 27th.
April 2023 - The building and parking plan, as well as building layout on site are finalized and the project is ready for Development Permit (DP) submission. A pre DP-meeeting occurred with civics to help smooth out any rough edges on the project in advance of the formal submission. Next step will be the DP submission process, and some waiting period associated with this process.
March 2023 - We held our OHCL AGM on Mar-09 and shared many community league updates, including a preview of the current design of the hub project. We received some feedback, and are taking it back to the project committee.
February 2023 - Its a new year and we continue to meet every 2 weeks. We have finalized the floor plan and layout, with just a few minor details to tweak. Expect some 3D renderings to be shared soon. Much of our recent work has been on landscape planning. Working with our landscape architect, we have a first draft completed. See below for a few teasers that are not finalized, which are meant to provide an idea of what we are working towards. They represent a step towards a finished product as we ensure the messages we heard from our community are represented in every aspect of the design. The minute we have more detailed official sketches for you, they are going to be posted. We are beyond excited for this moment!
Development Permit Submitted!
2022 - Design Phase Initiated
December 2022 - We continue to meet every 2 weeks with the hub advisory and design committee to go over building layout, utilization and vision. The committee is tasked with ensuring the design meets the previously determined needs, which were derived from your feedback during the past 4 years of engagement as seen below. We are starting to see the contours of the design come into view, and have a very solid layout coming together. The committee will soon have some design sketches and 3D views ready to present to our community. We expect these to be available mid-January. Stay tuned, this will be a big announcement!!
The high-level components of the building are covered below, but in summary...the final building will be staged in two phases. Phase 1 (2023) will focus on medium-gathering spaces and community functions, with indoor-outdoor components, storage, food serving area/kitchen, and spaces that support our current activities such as Winter Festival, art and cooking classes, wine & paint nights, movie nights, morning café, and other events you often see around the community. Phase 2 (2025 onward) will focus on the more traditional great-hall that you often see in many communities that would support larger gathering events, weddings, larger celebrations and other catered events. Phase 2 would also be expected to have a larger commercial kitchen space, full size outdoor skate/hockey rink, lighting, a winter sport warming-shelter/change room, outdoor bathroom, and additional washroom/building areas to support a larger hall such as an expanded foyer and parking. There will be opportunities for several mini-phases in between 1 and 2, including the addition of solar and green energy services, and IT, furnishing or finishing upgrades. The phased approach is required due to the recently inflated costs of construction, but will also allow the community some time to grow into the existing space, and allow us an opportunity to demonstrate future need.
The final components could (will?) change, but at this point Phase 1 is expected to have:
a welcoming foyer/entry way. This unspecified space could support ad-hoc socializing, a winter-warming area, small market space, and casual food service events (~600 sqft)
a community lounge for casual social events and small gatherings. This area is envisioned to have sofas, book shelves, board games, a fireplace and a food serving area for small gatherings (~500 sqft)
a community club house room with a multi-purpose feel for more structured events such as team gatherings, youth programs, birthdays, classes and meetings (~500 sqft)
a large outdoor entertainment area, with the plan to have an outdoor kitchen. The vision is to have a gas or wood pizza oven, with barbeque and fire pit. This area would have some weather protection such as rain, and sun shading, with tables to sit at. Vision of this is an outdoor 'café' feel (~1200sqft)
an indoor kitchen space, suitable for small catered event support, that is accessible to both rooms and the outdoor spaces. (~150sqft)
two small offices for our community league, and our building partner TRSA (Terwillegar-Riverbend Soccer Association) (~120sqft each)
various storage and support areas, including a large storage area to support the local soccer program needs (~1500sqft total)
indoor washrooms, mechanical, and support areas as expected
accessible parking. One goal of this is to help mitigate existing congestion on Leger Way/Road, and will be tucked down west-ward long Leger Road, away from existing congestion on Leger Way. Potentially, this could also provide a drop-off area for parents during school times, although that is not finalized.
During our engagement opportunities, we have heard that there are a lot of existing congestion and traffic issues along Leger Way at Leger Road during school pickup/drop off. There are also parking issues along Leger Way, as well as snow-clearing and pedestrian concerns. We are incorporating this into the building design, layout and land use to ensure that the building location and flow draws parking and traffic away from those areas as much as possible. We have also been actively supporting StreetLabs in our area to help mitigate and trial innovative solutions in advance of any construction to see what works best for our community.
November 2022 - Oak Hills President, Mike Boychuk, receives the Queen Elizabeth II Platinum Jubilee Medal for his work in the community and towards this project! In his keynote address, covering the history & roots of our neighbourhood, Mike shares the journey our community has embarked on, and how we find ourselves on course to build a community hub building in 2023. From our early roots, through initial dreams, all the way into needs assessments, business case and concept, he speaks to why community is vital to our livelihood and happiness. Please note: tragically, Mike passed away in 2023 while mountain biking with friends. His vision and memory will be carried forward by us. We were fortunate to have had Mike along for our journey, leading the Community Hub project for many years. Have a listen to his award presentation, recorded about 1 year prior to his sudden, untimely passing....
October 2022 - We are VERY excited to report that on Oct 25th the Oak Hills Community Hub committee completed its first official design phase meeting with TR Shaw Project Management, Stanley Construction, Croy Architecture, TRSA and of course OHCL. The meeting was held at the new Knottwood Community Hall, with each future meeting to be held at a new hall/location for inspiration/ideas. Now that the design phase is in full swing, we will be meeting every 2 weeks for the next 2-3 months. The next Hub meeting is at Chappelle Gardens Social House on Nov 8th. Future meetings are being considered at the new Ridge Community Hall, Whitemud Creek, and Laurier Heights. If you know of an inspirational space for a meeting, let us know so we can check it out!
The commitment for this project, which is Phase 1 of the overall final Hub plan, is to be shovels-in-the-ground spring 2023 with a target Phase 1 completion of Dec 30, 2023. This is ambitious, but the team is working to keep this on track and on budget ($1.54M for Phase 1 construction). Phase 1 requirements are: 1000 sqft storage (TRSA), TRSA & OHCL offices (3), General Storage space, Large gathering kitchen, mechanical, janitor and electrical rooms, Lounge, Club House, Community Garden, Interior Water Closets, Exterior accessible water closet, Lit snow mound rink, Toboggan Hill Space, Outdoor Patio/BBQ area.
Early 2022 - we have engaged a project management firm, have a stable funding model, and also have drafted an operational budget/business case to ensure the long-term success of the final product. We anticipate a shovels-in-ground date of early 2023.
This year we will be reaching out once again to get focused and specific detailed design information from YOU! Sign up for our newsletter to keep in the loop, get involved by joining the community hub committee, or attend our AGMs and monthly board meetings for more information.
Do you know what else is planned for the area near you, and how our community hub fits in to the larger community around us? Check out the concept map for the Bryan Anderson Athletic Grounds area.
Future Oak Hills Community Hub (red)
Future Edmonton Public Library (blue)
Future Artificial Turf Facility/Multi-sport & Track (green)
Future K-8 public school (yellow)
2020 - Major Funding Milestone Reached, Sourcing Project Manager, Architect, Builder
The Community Hub Project Committee has been working on tight timelines for grants, partnerships and other funding streams to get our anticipated Oak Hills Community Hub to detailed design phase. This has taken a lot of work by the committee, as well as the entire community league board.
We have VERY exciting news to share this month regarding approvals and funding! The community hub project has reached its mid-level funding threshold of $1.7M by being successful in both civic and provincial grants, and through partnerships with stakeholders. The community league has also received agreements for land use from the City of Edmonton at Leger park, near the playground at AJM school.
This represents a MAJOR accomplishment and milestone for the community hub project, as the next steps will include detailed design and further community engagement. Stay tuned by signing up for our newsletter.
WE NEED YOU!! Get involved with the committee to support its work, or join as a member to share your vision.
See below for some conceptual sketches, layouts and graphics that will inspire our project moving forwards.
Our Lead Partners
Conceptual Sketches/Layouts
2019 - Developing our Business Case, Well-Being Survey, Project Planning
We have now establish several concepts and a business case for a community hub development in Oak Hills! Based on your extensive and ongoing feedback we have clearly heard your wants and needs to create community and sustain recreation, socialization and neighbourliness in our area.
The community hub planning committee has been in full swing for about 1 year, and has accomplish a LOT of ground work in this time. The committee has secured grants, funding, stakeholder commitments, and developed a sound business case for the development, construction and operation of a community hub.
The vision is for more than a building with just four walls. This will be a place of community gathering, that brings all walks of life together from all corners of our neighbourhood and surrounding areas. Our relationships span further than the boundaries of our community, and so too should the reach of our community hub.
Want to participate or have an impact on the planning of this great feat? Send us an email and we will connect you with the hub planning committee.
We have completed our well-being impact analysis, a tool to help us develop a business case for this project and better understand our communities needs.
2018 - What We Heard, 5-Year Strategic Plan Developed
2017 - Community Neigbourhood Survey & Recreational Needs Assessment
The 2017 Programming Needs Assessment survey and consultation, which included an open house and online survey, came to a close at the end of September 2017. The feedback received during the open house and the results of the survey have been synthesized into a Tableau presentation below -- just scroll and explore!
The board will then begin to compile the feedback results into a What We Heard document to take back to our community.
Early 2019 we will be conducting phase two of our engagement process to re-survey our community having implemented these programming needs. This second survey will be focused more directly on personal recreation needs and community well-being, with a focus being the development of our community league land allotment at Leger Park plus the refreshment of the Carter Crest playground and park space.
2013 - Initial Discussion and Alignment of Objectives
The board began early discussions and research on how to best utilize our Community League Licensed Land area in the South East corner of Terwillegar Heights District Park (now named Bryan Anderson Athletic Grounds). Like other members of the Edmonton Federation of Community Leagues (EFCL), Oak Hills CL has a Tripartite License Agreement for use of a site on City land. The Agreement between the City, EFCL and the Community League outlines the terms and conditions for use of the site owned by the City and occupied by a Community League. The board began aligning some of its objectives in preparation for the required needs assessment, community engagement, surveys and other steps to get the process started.
2009 - A Beginning for Oak Hills
The Oak Hills Community League (OHCL) was founded as a not-for-profit society in 2009 by neighbours to meet the needs and interests of their community. OHCL worked to engage our community on issues and projects within our two neighbourhoods, Leger (Whitemud Oaks) and Carter Crest (Whitemud Hills). OHCL is formally recognized by the City of Edmonton as part of a network of neighbourhood-based organizations operating under the umbrella of Edmonton Federation of Community Leagues (EFCL).
OHCL provides inclusive recreation and social programs such as sports, family events, community gathering, personal development opportunities, movie nights, and more. We endeavor to continue developing amenities that bring neighbours together such as a community building and grounds, rinks, playgrounds, tennis courts, and basketball courts. OHCL considers its members and the community at large when advocating on issues of interest to the appropriate order of government or other organizations regarding traffic issues, new developments, housing, crime prevention, and other community issues.
Before our community league was formed, our neighbourhood was developing...
Terwillegar Rec Centre (built 2009)
The $160-million facility at Terwillegar Drive and 23rd Avenue was Edmonton’s first new recreation centre since the Mill Woods complex opened in the early 1980s. Several of OHCLs initial board members were also key members of TRAC (Terwillegar Riverbend Advisory Council) which was a major player in getting the rec centre built.
Terwillegar Riverbend Advisory Council / TRAC (formed 2003)
TRAC was formed as a society on December 1, 2003 under the direction of three active community leagues in the Terwillegar/Riverbend area at the time: Riverbend, Brookview and The Ridge. It has expanded over the years and now includes the neighborhoods of Brander Gardens, Brookside, Bulyea Heights, Carter Crest, Falconer Heights, Haddow, Henderson Estates, Hodgson, Leger, Magrath, MacTaggart, Ogilvie Ridge, Ramsay Heights, Rhatigan Ridge, South Terwillegar, Terwillegar Gardens, Terwillegar Towne, & Greater Windermere
Leger / Whitemud Oaks (developed late 1990s - mid 2000s)
The Leger neighbourhood was named after a long serving Edmonton politician, Edmund Hugh Leger, who was first elected to City Council in 1959 and went on to serve as an alderman for 25 years. All homes are oriented along curvilinear streets, with higher density residential developments located along arterial and collector roads in close proximity to transit routes, commercial amenities, and recreational facilities. A pedestrian and bicycle pathway system connects the residential areas with the commercial site in the southeast and the institutional and recreational amenities in the west.
Carter Crest / Whitemud Hills (developed early-mid 1990s)
Carter Crest is named after Robert I. Carter (1858-1931) who was a Canadian government agent who advised Americans on their immigration prospects to Canada. He purchased a farm in what is now Terwillegar Park, naming it Riverside Farm. Carter Crest was designed to integrate seamlessly with surrounding residential areas, and to provide an attractive community for its residents. Robert Carter Park, located in the northeast portion of the neighbourhood, provides residents with open space, and a system of pathways provides for efficient pedestrian and bicycle access throughout the neighbourhood.
Terwillegar Rec Centre Being Built: Photos